St. Paul’s School – Barnes, London

,

Technical Arts were employed by DES Electrical to offer expert input on the supply and delivery of distributed audio systems for the Phase I development.

We were required to work in partnership with DES Electrical, and the wider client team to ensure not only compliance with the design, but a robust and aesthetically considered end result.

Distributed and zoned audio was provided over three floors in all general promenade areas, classrooms and administration/teaching support areas.

Additional performance systems were also provided in the multi-purpose Dining Hall and the Library.

Paging and class change systems were integrated into the new build via a pre-existing IP based site wide network.

Having achieved a snag free handover for Phase I of the scheme, Technical Arts have been retained to deliver Phase II due for completion in September 2019.